What is a fixed price pool quote?
A fixed price pool quote fixes the contract price for the work it describes, not its exclusions or allowances. This covers how Queensland's QBCC Act and the NSW Home Building Act treat a fixed price, the QBCC's 30% allowance warning and the home warranty consequence. It includes a checklist of exclusions, from rock and excavation to the fence, council approval and landscaping.
A fixed price pool quote fixes the contract price for the work it describes, not what it excludes or leaves as an allowance. Under Queensland's QBCC Act, a contract with prime cost items and provisional sums can still be fixed price. The QBCC warns that allowances of 30% or more of the price add risk for owners.
The short answer
- In Queensland, fixed price is defined by what it is not. The QBCC Act (Schedule 1B, section 1) calls a contract cost plus when its price ‘cannot be accurately calculated’ at signing ‘even if prime cost items and provisional sums are ignored’. So a contract that includes allowances can still be a fixed price contract.
- The QBCC's warning line is 30%. Its contracts guide says contracts with 30% or more of the price covered by allowances carry added risk for owners, especially on a tight budget.
- The price has to be on page one. In Queensland a fixed contract price, without allowances, and a price change warning must appear on the first page of the contract schedule. In NSW the Home Building Act requires the price on the first page and a warning next to it if the price can vary.
- Whether your contract is fixed price affects your insurance. A Queensland Home Warranty Scheme non-completion claim requires a fixed-price contract. The QBCC says non-completion assistance is not available under cost plus or construction management contracts.
- In Queensland, the soil test comes before you sign. Schedule 1B section 31 requires the contractor to get foundations data such as soil tests before entering the contract. The QBCC says this is almost always required for an inground pool.
| Clause in the quote | What it does to the price | What the fixed version looks like | Where the rule comes from |
|---|---|---|---|
| Rock or unsuitable ground ‘excluded’ or ‘at cost’ | No limit: the price moves by whatever is found | A provisional sum with a stated rate per m³ or per hour beyond it | QBCC Act Sch 1B s10: a provisional sum only where no definite amount can be stated after all reasonable enquiries |
| ‘Price subject to soil test’ or ‘subject to engineering’ | The price is not set until a report you have not seen exists | Soil test done and engineering priced before signing | QBCC Act Sch 1B s31 (Qld): foundations data required before the contract; ‘almost always’ needed for an inground pool |
| No provision for rock or wet weather at all | Leaves the argument until the machine finds it | A written clause on how unforeseen ground and weather are handled | QBCC build-a-pool guidance: the contract should include provisions for unforeseen events, e.g. rock or wet weather |
| Prime cost items (tiles, coping, lights, heater) | Moves with your selection, plus the builder's markup, plus GST | Items chosen and priced before signing | QBCC schedule example: a $1,500 allowance + 10% markup + GST = $1,815 |
| Provisional sums (rock, retaining, extra excavation) | Reconciles to the actual cost of the service | Allowance plus the rate that applies once it runs out | QBCC Act Sch 1B s10; must be calculated with reasonable care and skill (s26) |
| Allowances total 30% or more of the price | Nearly a third of the contract price can still move | Allowances cut to the items that genuinely cannot be priced | QBCC contracts guide: 30% or more carries ‘added risk for owners’ |
| Fencing, paving or landscaping not mentioned | Not in the price at all: a second budget | The quote says in writing whether the barrier and surrounds are included | QBCC build-a-pool guidance: confirm exactly what is included, e.g. ‘does the quote include fencing?’ |
| No price on page one (Qld), or no warning next to the price (NSW) | Either not a fixed price contract or a non-compliant one, whatever the salesperson said | A dollar figure on page one of the schedule or contract | QBCC contracts guide; Home Building Act 1989 (NSW) s7(4)–(5) |
What does ‘fixed price’ legally mean on a pool contract?
Queensland's legislation does not define fixed price directly. It defines the opposite. Section 1 of Schedule 1B of the Queensland Building and Construction Commission Act 1991, as quoted by the QBCC, calls a contract cost plus when the amount the builder is to receive ‘cannot be accurately calculated when the contract is entered into, even if prime cost items and provisional sums are ignored’.
The last clause of that definition matters. A contract counts as fixed price if its price can be calculated once the allowances are set aside. So a pool contract carrying a $6,000 rock allowance and an $8,000 tile allowance is still, legally, a fixed price contract. The fixed part is everything outside those two lines.
A fixed price pool contract fixes the price of the work it describes. It does not fix the allowances inside it or anything it leaves out.
The two allowance types work differently, and each has its own page: what a prime cost item is (fittings you have not chosen yet) and what a provisional sum is (services that cannot be priced yet, like rock). If the whole price is open, you are looking at a different contract type. Should I sign a cost plus pool contract covers it, including why Victoria rules it out for a pool.
Where the fixed price has to appear, by law
There is a quick check on page one of the contract.
Queensland. The QBCC's guide to domestic building contracts summarises the required warranties. The contract price, ‘if a fixed amount, without allowances’, and a price change warning must be stated on the first page of the contract schedule. The warning sets out any contract terms that could make the price go up or down. If the price is not fixed, the schedule must state the method for calculating it, including any allowances.
New South Wales. Section 7 of the Home Building Act 1989 says that if the contract price is known, it ‘must be stated in a prominent position on the first page of the contract’. If the price is not known or may be varied, the contract must carry a warning to that effect with an explanation of the clause that allows the variation, ‘placed next to the price’.
Rule of thumb for both states: if page one shows a method instead of a number, you do not have a fixed price contract. If page one shows a number with a warning beside it, read the warning. It lists every way the number can move.
Once work starts, changes to the fixed scope are variations, and in Queensland they must be agreed in writing before the work is done. What a variation on a pool contract is covers the timing rules.
The 30% line: when a fixed price stops meaning much
The QBCC gives a threshold for this. Its guide to domestic building contracts says contracts with a high proportion of the price covered by allowances, ‘e.g. 30% or more’, carry added risk for owners, especially owners on a tight budget, because of the uncertainty about the final amount. It asks owners to check, before signing, what share of the price is fixed and what share is variable.
Worked example (illustrative figures, not a benchmark). Two quotes for the same pool:
- Quote A: $72,000. Allowances: tiles $5,000, lights $1,500, heater $4,000 (prime cost items), plus rock $6,000 and retaining $5,000 (provisional sums). Total allowances $21,500, or 29.9% of the price, just under the QBCC's 30% example.
- Quote B: $78,000. The tiles, lights and heater have been chosen and priced. One $6,000 rock provisional sum remains. Allowances are 7.7% of the price.
Quote A is $6,000 cheaper on paper. But nearly a third of its price can still move, and every prime cost item that moves carries markup and GST on top. The QBCC's own schedule example turns a $1,500 allowance into $1,815 with 10% markup and GST, and the markup rate is whatever your contract states. The comparison that matters is the fixed share of each quote, not the headline.
To work out your own figures, add up every prime cost item and provisional sum and divide by the contract price. For the other lines worth lining up side by side, see what differs between pool quotes.
Why whether your contract is fixed price affects your home warranty
This is where the label has real consequences in Queensland.
The QBCC's non-completion page sets out who can claim under the Queensland Home Warranty Scheme when a builder cannot finish. One eligibility criterion is that ‘the contract was for a fixed price’. The QBCC's page on cost plus and construction management contracts is explicit: non-completion assistance ‘is not available to homeowners when cost plus or construction management contracts are used’.
There is a second link. The QBCC may pay you less on a non-completion claim if the contract was underquoted by more than 30%. Its own example is a $200,000 contract for work actually worth $270,000, where the claim is reduced by $70,000. A quote that is unrealistically low can reduce the insurance payout that is supposed to protect you if the builder fails.
For what the scheme covers on a pool, see the Queensland Home Warranty Scheme on a pool. Other states have their own thresholds, listed in builder's warranty insurance by state.
How to turn a ‘fixed price’ quote into a price that is actually fixed
Most of the variable parts of a pool quote can be fixed before you sign, if you do it in the right order.
- Get the ground investigated first. In Queensland, section 31 of Schedule 1B requires the contractor to obtain foundations data, such as soil tests and contour surveys, before entering the contract. The QBCC says this is almost always required for an inground pool. A quote that says ‘subject to soil test’ is asking you to sign before that step is done. See whether you need a soil test before building a pool.
- Choose your fittings before signing. Every tile, light and heater you choose and get priced is one less prime cost item that can move.
- Keep only real unknowns as provisional sums, each with a rate. Rock is a genuine unknown. The rate that applies after the allowance runs out is what makes quotes comparable.
- Get the scope in writing. The QBCC's pool-building guidance tells owners to confirm exactly what the price includes, such as fencing, surrounds and landscaping.
- Check page one. You want a number, not a method.
Ask each builder to fix every line that can be priced and to put a rate on every line that cannot. A builder who does that has given you a fixed price quote in practice, not just in name.
Ask several builders the same questions so their answers can be compared. You can compare pool quotes from builders who work in your area, and why a pool cost more than the contract covers what happens when a quote was not fixed where it mattered.
Common questions
Does a fixed price pool quote mean the price cannot change?
Can a contract with provisional sums still be fixed price?
How much of a pool quote should be allowances?
Is rock usually excluded from a fixed price pool quote?
Why does a fixed price matter if my builder goes broke?
Sources
- QBCC — Cost plus and construction management contracts (QBCC Act Sch 1B s1 definition)
- QBCC — Domestic building contracts: information for owners and contractors (PDF)
- QBCC — New home construction contract, prime cost items schedule (PDF)
- QBCC — Home warranty for non-completion claims
- QBCC — Build a pool
- Home Building Act 1989 (NSW), section 7 — NSW Legislation
General information only, current at 2026-09-26. Pool rules differ by state and by council, and penalty amounts are updated regularly. Confirm your own obligations with your council or a registered inspector before acting.
Thinking about a pool?
Compare quotes from builders who work in your postcode. One form, no obligation.
Get my quotes