The fence you are paying for at the end of the job is not the only fence the build needs. Victoria requires a site fence before any excavation starts, and a second barrier between your existing house and the pool construction area. Both are inspected. Both cost money. And because they are temporary, they are one of the easiest things for a quote to quietly leave out — which is exactly why comparing quotes on price alone misleads.

Updated 2026-09-18 2 sources cited

Yes. In Victoria a site fence must be in place before any excavation for the pool commences, and a site fence or hoarding must separate an existing dwelling from the pool construction area. Once the excavation holds more than 300mm of water, a barrier complying with AS1926.1-2012 is required.

The short answer

  • Before the digger, not after. The site fence must be in place before any excavation for the pool or spa commences — it is a precondition of starting, not a step in the sequence.
  • Regulation 116(3) requires any excavation to be fenced or otherwise guarded against being a danger to life or property.
  • A site fence or hoarding must be provided between an existing dwelling and the pool construction area. Where the pool goes in alongside a new house, an additional site fence is required.
  • Once the excavation, pool or structure holds more than 300mm of water — rain included — a barrier complying with AS1926.1-2012 must be erected and maintained.
  • Completion of the precautions is one of the mandatory notification stages under regulation 169. The surveyor inspects it.
What has to be fenced during a Victorian pool build, and when
Stage of the buildWhat is requiredStandard it must meet
Before any excavation beginsSite fence in placeDesign agreed with the relevant building surveyor and detailed in the building permit
Excavation openExcavation fenced or otherwise guardedRegulation 116(3) — against being a danger to life or property
Throughout, where a dwelling already existsSite fence or hoarding between the dwelling and the construction areaAgreed with the surveyor
Pool built alongside a new houseAn additional site fence between the pool construction areaAgreed with the surveyor
Excavation or shell holds more than 300mm of waterComplying safety barrier erected and maintainedAS1926.1-2012
Gate fitted in the site fenceRecommended to comply with AS1926.1-2012AS1926.1-2012
No gate fittedBarrier stays closed except when access is needed and people are present the whole time—

Why the site fence comes before the excavator

The ordering is the whole point, and it is easy to read past.

The Victorian Building Authority's practice note lists, among the requirements a pool must comply with, that “a site fence must be in place before any excavation for the pool or spa commences”. Not during. Not by the end of the first day. Before.

The reason is in the same document's description of the hazard: a pool excavation and a shell under construction are a fall hazard, and they hold ground water and rain water. The most dangerous single day of a pool build is the day the hole exists and nothing else does — no coping, no barrier, no water to make it obviously a pool, and often no one on site after 3pm.

So the protection has to exist before the hazard does, which means the fence is a precondition of starting rather than a task in the program. If someone arrives to excavate and there is no site fence, the correct response is that work does not start that day.

This also explains something owners find odd: your surveyor may require a complying AS1926.1-2012 barrier to be installed and inspected immediately after the excavation is completed — particularly for fibreglass pools, where the shell will hold water almost straight away.

The second fence almost nobody expects

Here is the requirement that surprises people, and it is unambiguous in the practice note:

“A site fence or hoarding must be provided between an existing dwelling and the pool construction area.”

Not around the property. Between your house and the hole.

Think about who that protects, and it is obviously right. The public is not the main risk on a suburban pool build — the street is fenced and the gate is shut. The risk is the household. A three-year-old who lives at the address, who has watched the excavator all week, and for whom the back door is the most familiar thing in the world.

And where the pool is going in at the same time as the dwelling itself, an additional site fence is required between the pool construction area. Two builds, two sets of trades, two hazards.

Practically, this is the requirement most likely to be treated casually, because it looks like an inconvenience inside your own property rather than a safety measure. It is worth being the client who insists on it. The barrier between your back door and an open excavation is the one that is actually load-bearing.

Gates, and the rule for when there is no gate

The practice note is careful here, and the second half of it is the part to remember.

Where a gate is installed in the site fence or hoarding, it is recommended that it comply with AS1926.1-2012, so that restricted access by young children is maintained. Same standard as a permanent pool gate: self-closing, self-latching, the lot.

Where no gate is installed, the barrier must remain in place except when access to the pool area is required — and people must be present at all times while it is open.

That second rule is a genuinely different discipline from a gate, and worth saying out loud to whoever is on site: the panel does not come out for the morning. It comes out while someone is working, and it goes back when they leave, including for lunch and including at the end of the day.

It is also a reasonable thing for you to check, because you are the one at home. A site fence with a panel leaned against a wall since Tuesday is not a site fence. If you see it, say so — and if it persists, your relevant building surveyor is the person to tell. If a surveyor becomes aware a precaution has been moved or altered so it no longer complies with the building permit, they can issue a direction to fix, orally or in writing. If it is given orally and not rectified within 7 days, a written direction must follow. We cover that escalation in what a direction to fix means on a pool.

Check it is in the quote, because it is a real cost

Temporary fencing costs money. Hire, delivery, installation, the second run between the house and the works, weeks or months of hire, then removal.

We are not going to publish a hire rate, and we would rather explain why than guess: we could not verify a temporary fencing hire price at any source that was not selling temporary fencing. Every figure available is a vendor's own advertised rate, which is a price list rather than a market. Publishing one would be advertising with a citation on it, and the range between suppliers and regions is wide enough that a single number would mislead more than it helped.

What we can tell you is where it hides in a quote, which is more useful:

  • An itemised quote that names site fencing has priced it. Good.
  • A quote that says “site establishment” or “site costs” may include it. Ask which.
  • A quote that mentions neither has either absorbed it or left it out, and those two have very different consequences for you later.
  • A quote that excludes it explicitly is being honest, and you now have a cost to add before comparing.

This is the general problem with comparing pool quotes: the cheapest number is frequently the one with the most left out of it. Ask every builder the same question — “Is temporary site fencing included, and is the fence between the house and the works included?” — and the prices become comparable. Compare pool builder quotes on scope, and see what actually differs between pool quotes.

Common questions

When does the site fence have to go up?
Before any excavation for the pool or spa commences. VBA Practice Note 05-2018 lists it among the requirements a Victorian pool must comply with, and regulation 116(3) separately requires any excavation to be fenced or otherwise guarded against being a danger to life or property. The practice note is published in full by Mornington Peninsula Shire.
Do I need a fence between my house and the pool works?
In Victoria, yes. A site fence or hoarding must be provided between an existing dwelling and the pool construction area. Where the pool is being constructed at the same time as the dwelling, an additional site fence is required between the pool construction area.
Who pays for temporary fencing on a pool build?
It is normally the builder's cost and should appear in the contract price, but it is a common omission from cheaper quotes. Ask explicitly whether site fencing — including the fence between the dwelling and the works — is included, and get the answer in writing before comparing quotes on price.
What if it rains and the excavation fills with water?
As soon as the excavation, pool or structure contains more than 300mm of water, a safety barrier complying with AS1926.1-2012 must be erected and maintained. The rule makes no distinction between water you put in and water that fell in, which is one reason surveyors often require a complying barrier immediately after excavation.
Does the same rule apply outside Victoria?
The principle is the same everywhere — an open excavation must be secured, and a pool holding water needs a complying barrier — but the specific requirements and the wording differ by state. The detail here is Victorian, from the Building Regulations 2018 and VBA Practice Note 05-2018. Check your own state's regulator for the local equivalent.

Sources

General information only, current at 2026-09-18. Pool rules differ by state and by council, and penalty amounts are updated regularly. Confirm your own obligations with your council or a registered inspector before acting.